P-060 - Public Project Site
-
27th November 2024, Carpark onsite
Hi All ,
Just iterating the importance of the no carparking onsite at any time . We understand its frustrating but this is important for the the hospital our client and Erilyan that we abide by there rules .
All trades are to drop off tools and materials for a maximum of 10 mins noting that hospital deliveries take priority which means you are required to remain on the Avenue until the loading zone is clear if there is congestion .Please see the Erilyan site team if you require anymore information on this matter .
See below below email from Andrew Stuart ( Site manager ) regarding no parking onsite.
Thanks,
Hi All,
As we have just commenced work on the Avenue Private Hospital project, we must be very mindful that we are working in a live environment.
Today we had a vehicle parked out the front of our site compound and a delivery truck could not gain access to the Hospital as the ute was in the way. This delivery truck was from BOC (gas truck) and could not make the delivery to the Hospital.
Each morning it is ok to park out the front of the compound to quickly unload tools, and then move the vehicles, Hospital deliveries will always take priority.
Please talk to all your site employees and make them aware. I will reiterate this each morning in the prestart. I have attached our site layout plan for your information.
Please note significant penalties including re inductions to site will apply
Current Site Weather
Last Updated at: 12:21 PM
Wind Speed: 24KMH
Max. Wind: 46KMH @1:21 AM
Rain since 9AM: 0.0mm
Gust: 28KMH
Max Gust: 56KMH @12:21 AM
Observation Location - St Kilda Harbour RMYS, VICTORIA
Time Zone - Australian Eastern Standard Time
Forecast - Monday, 2 February
Sunny.
Min: 12C Max: 32C
Chance of Rain: 5%
Forecast Location - Melbourne, VICTORIA
Time Zone - Australian Eastern Standard Time
Tomorrow - Tuesday, 3 February
Partly cloudy.
Min: 19C Max: 31C
Chance of Rain: 10%
-
EG-DE-CO-PLN-003_Site_Emergency_Management_Plan_REV_4_28.5.2025 (DS)
Uploaded 11/06/2025
save_alt Download -
EG-DE-CO-PLN-003_Site Emergency Management Plan REV 4 24.2.2025
Uploaded 12/05/2025
save_alt Download -
P060 TAH EG-DE-CO-REG_Quality Planning Matrix & ITP Checklist Register
Uploaded 31/01/2025
save_alt Download
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.
Do you know the PPE Requirements for this site?
Ensure you have the correct safety equipment for your first day at the site.
Get started working sooner when you arrive on site.
Complete your site registration online at your convenience and save yourself time.