P-060 - Öffentlicher Projektstandort
-
27th November 2024, Carpark onsite
Hi All ,
Just iterating the importance of the no carparking onsite at any time . We understand its frustrating but this is important for the the hospital our client and Erilyan that we abide by there rules .
All trades are to drop off tools and materials for a maximum of 10 mins noting that hospital deliveries take priority which means you are required to remain on the Avenue until the loading zone is clear if there is congestion .Please see the Erilyan site team if you require anymore information on this matter .
See below below email from Andrew Stuart ( Site manager ) regarding no parking onsite.
Thanks,
Hi All,
As we have just commenced work on the Avenue Private Hospital project, we must be very mindful that we are working in a live environment.
Today we had a vehicle parked out the front of our site compound and a delivery truck could not gain access to the Hospital as the ute was in the way. This delivery truck was from BOC (gas truck) and could not make the delivery to the Hospital.
Each morning it is ok to park out the front of the compound to quickly unload tools, and then move the vehicles, Hospital deliveries will always take priority.
Please talk to all your site employees and make them aware. I will reiterate this each morning in the prestart. I have attached our site layout plan for your information.
Please note significant penalties including re inductions to site will apply
Aktuelles Wetter am Standort
Zuletzt aktualisiert um: 14:21
Windgeschwindigkeit: 28KMH
Max. Wind: 46KMH @01:21
Regen seit 09.00 Uhr: 0,0mm
Windböe: 32KMH
Max. Windböe: 56KMH @00:21
Beobachtungsstandort - St Kilda Harbour RMYS, VICTORIA
Zeitzone - Ostaustralische Normalzeit
Vorhersage - Montag, 2 Februar
Sunny.
Min.: 12C Max.: 32C
Niederschlagswahrscheinlichkeit: 5%
Prognose Standort - Melbourne, VICTORIA
Zeitzone - Ostaustralische Normalzeit
Morgen - Dienstag, 3 Februar
Partly cloudy.
Min.: 19C Max.: 31C
Niederschlagswahrscheinlichkeit: 10%
-
EG-DE-CO-PLN-003_Site_Emergency_Management_Plan_15.9.2025
Hochgeladen 08.12.2025
save_alt Herunterladen -
EG-DE-CO-PLN-001_Construction_Management_Plan_15.9.2025
Hochgeladen 08.12.2025
save_alt Herunterladen -
EG-DE-CO-PLN-003_Site_Emergency_Management_Plan_REV_4_28.5.2025 (DS)
Hochgeladen 11.06.2025
save_alt Herunterladen -
EG-DE-CO-PLN-001_Construction_Management_Plan_REV12 (DS)
Hochgeladen 11.06.2025
save_alt Herunterladen -
EG-DE-CO-FRM-001_Project Risk Assessment REV B 3.2.2025
Hochgeladen 12.05.2025
save_alt Herunterladen -
EG-DE-CO-PLN-003_Site Emergency Management Plan REV 4 24.2.2025
Hochgeladen 12.05.2025
save_alt Herunterladen -
EG-DE-CO-PLN-001_Construction Management Plan REV 24.2.2025
Hochgeladen 12.05.2025
save_alt Herunterladen -
P060 TAH EG-DE-CO-REG_Quality Planning Matrix & ITP Checklist Register
Hochgeladen 31.01.2025
save_alt Herunterladen
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.
Kennen Sie die PPE-Voraussetzungen für diesen Standort?
Stellen Sie sicher, Sie an Ihrem ersten Tag am Standort über die korrekte Sicherheitsausrüstung verfügen.
Fangen Sie früher mit der Arbeit an, wenn Sie vor Ort ankommen.
Füllen Sie Ihre Standortregistrierung online aus und sparen Sie damit Zeit.