P-060 - Site du projet public
-
27th novembre 2024, Carpark onsite
Hi All ,
Just iterating the importance of the no carparking onsite at any time . We understand its frustrating but this is important for the the hospital our client and Erilyan that we abide by there rules .
All trades are to drop off tools and materials for a maximum of 10 mins noting that hospital deliveries take priority which means you are required to remain on the Avenue until the loading zone is clear if there is congestion .Please see the Erilyan site team if you require anymore information on this matter .
See below below email from Andrew Stuart ( Site manager ) regarding no parking onsite.
Thanks,
Hi All,
As we have just commenced work on the Avenue Private Hospital project, we must be very mindful that we are working in a live environment.
Today we had a vehicle parked out the front of our site compound and a delivery truck could not gain access to the Hospital as the ute was in the way. This delivery truck was from BOC (gas truck) and could not make the delivery to the Hospital.
Each morning it is ok to park out the front of the compound to quickly unload tools, and then move the vehicles, Hospital deliveries will always take priority.
Please talk to all your site employees and make them aware. I will reiterate this each morning in the prestart. I have attached our site layout plan for your information.
Please note significant penalties including re inductions to site will apply
Météo sur le site actuel
Dernière mise à jour: 14:21
Vitesse du vent: 28KMH
Max. Vent: 46KMH @01:21
Précipitations depuis 9 h: 0,0mm
Rafale de vent: 32KMH
Rafales max: 56KMH @00:21
Lieu d'observation - St Kilda Harbour RMYS, VICTORIA
Fuseau horaire - heure normale de l’Est de l’Australie
Prévision - lundi, 2 février
Sunny.
Min: 12C Max: 32C
Risque de pluie: 5%
Lieu en prévision - Melbourne, VICTORIA
Fuseau horaire - heure normale de l’Est de l’Australie
Demain - mardi, 3 février
Partly cloudy.
Min: 19C Max: 31C
Risque de pluie: 10%
-
EG-DE-CO-PLN-003_Site_Emergency_Management_Plan_15.9.2025
Téléchargé 08/12/2025
save_alt Télécharger -
EG-DE-CO-PLN-003_Site_Emergency_Management_Plan_REV_4_28.5.2025 (DS)
Téléchargé 11/06/2025
save_alt Télécharger -
EG-DE-CO-PLN-003_Site Emergency Management Plan REV 4 24.2.2025
Téléchargé 12/05/2025
save_alt Télécharger -
EG-DE-CO-PLN-001_Construction Management Plan REV 24.2.2025
Téléchargé 12/05/2025
save_alt Télécharger -
P060 TAH EG-DE-CO-REG_Quality Planning Matrix & ITP Checklist Register
Téléchargé 31/01/2025
save_alt Télécharger
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.